The bid by TLSL of Walnut was accepted as the lowest and best bid for the project in the amount of $486,483. TLSL was one of six bidders for the project, which included Parson Earthworks, Iuka, bidding $490,604; Pittman Construction, Corinth, $497,061; Rogers Group, Lawrenceburg, Tenn., $515,840; Buddy Ayers Construction, Corinth, $533,603; Rutledge Contractors, Tupelo, $576,494.
The work is expected to begin soon, with completion set at 90 calendar days.